Energetik Energy Centre Progress

Work is progressing well at Energetik Energy Centre in Enfield, where the structural steel frame of the energy centre is due for completion in the next fortnight.

Cladding is due to arrive during the first week of December, so we’ll have the thermal store area wrapped at low level by Christmas, ready for the thermal store installation which will commence mid-January.

By Christmas we will have the mezzanine floor level complete, together with the roof decking watertight. ​​​​​​​

District heating pipework continues across the Enfield Ditch and along the roads around Edmonton.