York Teaching Hospitals NHS Foundation Trust

Scarborough & Bridlington Hospitals Energy Upgrades

Executive Summary

After a successful project at York Teaching Hospital, Vital Energi were chosen to deliver similar energy management and generation projects at two of the Trust's other sites; Scarborough and Bridlington hospitals. The combination of demand reduction, followed by Combined Heat & Power engine installations and energy centre upgrades yielded large financial savings and reduced carbon emissions substantially.

  • stats-numerical
    £4.4m contract value
  • reducing-carbon
    Over 40,000 tonnes of CO2 reduction
  • ve-lighting
    13 month delivery period
  • reducing-carbon (1)
    15 year O&M Contract

Project Overview

After a successful energy scheme at York Teaching Hospital, the Trust wanted to make similar improvements at their Scarborough and Bridlington hospitals, reducing their energy spend and substantially decreasing their carbon emissions.

Both projects were procured as a joint contract through the Carbon & Energy Framework and, once again, we were chosen to design, install, commission, operate and maintain and act as the Energy Services Company (ESCo).

Our Solution

CJP 1396

We employed a dual approach on these projects.  Initially we focused on reducing demand through energy conservation measures.  Once we had undertaken the planning for this we could specify energy generating plant which would meet the new, reduced demand.

At both Bridlington and Scarborough, our energy reduction specialists saw the opportunity to upgrade light fittings from outmoded tube lighting to more modern, energy efficient lumens, which would not only save money, but improve the quality of lighting on the hospital premises.  All lighting upgrades were completed and commissioned ahead of schedule.  One all energy reduction measures have been identified, Vital Energi then designs the optimum energy generation solution

1 – Upgrading the energy infrastructure at Scarborough

At Scarborough Hospital, Vital Energi, along with their sister company Vital Efficienci, upgraded the Building Management System, modifying and improving panels to facilitate the newly installed equipment and installing heat meters to allow for accurate monitoring and measuring of energy. These improvements allowed the designers to specify a smaller 776kWe CHP engine which could run at full capacity, giving increased efficiency.  Additionally we installed the CHP heat distribution pipe network, 4MW composite steam boiler, HV electrical connection, steam/LTHW plate heat exchangers, lighting replacement scheme, pipework insulation and cavity wall insulation.

This CHP was delivered in a containerised unit specifically designed to acoustically reduce the amount of noise.   Due to the size of the equipment, it was delivered on an oversized vehicle and the delivery and placement of the engine had to be carefully planned.  It was then craned from the lorry and into place with only 50mm to spare at some points in the procedure

In addition to the CHP, Vital performed major modification works to the flue headers under instructions from the Trust, completing work in a single 12 hour shift, rather than the original 2 day estimate. Overall, the system will deliver a CO2 reduction of 2,129 per annum over the course of the 15 year contract.

2 – Identifying issues and Minimising Disruption at Scarborough

Scarborough Hospital called for a substantial number of client instructed variations completed during the project time frame due to issues uncovered by dilapidation surveys by the Vital Energi project team.  By identifying and addressing all issues it ensured the client had a more robust and reliable steam system and boiler houses and reduced the potential for system failure.

The project called for several phases of work which could have caused potential disruption to the hospital, but through careful management and liaison with hospital departments Vital were able to keep this to a minimum.  Vital would need to shut down the steam, domestic and low temperature hot water systems, but were able to schedule work for weekends and out of hours times to minimise disruption.  Similarly, when the project called for us to install low temperature hot water pipework across the main access route to the NHS stores and waste disposal areas we were able to schedule these works to have the least impact.

3 – Revolutionising the energy infrastructure at Bridlington

At Bridlington Hospital we installed a 238kWe CHP unit which will contribute towards reducing the hospital’s CO2 emissions by 676 tonnes per year, which is a reduction of approximately 44 per cent.  The CHP unit will supply all of the hospital’s night time electricity, over 50% of its day time electricity and make a substantial contribution to the heating and hot water supply.

We undertook the installation of the Supervisory Control And Data Acquisition (SCADA) system which allows for remote monitoring and control, providing accurate feedback on energy usage and performance which can be used to constantly improve the system, making it more efficient.  This system, which was installed at both sites, also includes a state of the art alarm system, alerting on-duty engineers via text messages, email and phone, allowing them to address any issues at the earliest point.

Solution detail

Vital won the project as they thought differently to others and came up with solutions others didn’t. Vital understood the Trusts requirements and provided significant contributions to realising our aspirations. Vital were the only company to consider keeping the steam network and retaining its reliability and that was what delivered the project successfully.

Brian Golding, York Teaching Hospital NHS Foundation Trust

Scarborough & Bridlington Hospitals Energy Upgrades

Download Case Study Scarborough & Bridlington Hospitals Energy Upgrades Case Study 1.52 Mb
Related case study

University of Edinburgh

Find out more